Friday, 15 March 2013

This week we poured 30% of the concrete foundations with the other 70% to be poured next week. We progressed on the road construction which will help to make Blackmoorfoot Road cleaner and have installed the Precast Lift Shaft.
 



 

Friday, 8 March 2013

This week we started digging the foundations, of which 30% is now ready for the concrete pour on Monday. Road construction and installation of the precast lift shaft are due to start next week.
 


 
 

Monday, 4 March 2013

The car park construction is now finished, permanent cabins are in place and the Foundation dig is due to start next Monday.