External Works are
progressing well here at Sandy Mount. Due to the lack of space on site the site
management have had to meticulously create a sequenced programme which would
allow the ground workers to work from the rear of the site to the front. The
team here at Sandy Mount are confident that the external works will continue
without hindrance and be complete in line with the
programme.
Friday, 24 January 2014
Wednesday, 22 January 2014
The Heat Is On...
This week saw some
really good news here at Sandy Mount. The plumbing contractors have been working
effortlessly to get the heating on so final decorations can continue. Most of
the trades who work inside now leave their jumpers at home as it is so warm
inside the building.
Monday, 6 January 2014
The team at
Sandy Mount would like to wish everyone a happy new year and we hope that
everyone enjoyed their Christmas break. The clock has started ticking for
completion of Sandymount so its all hand on deck. All of the plastering is
complete on the second and first floors and is nearly complete on the ground.
Decoration to both first and second floor is well underway in line with the
programme and by the start of next week we should see external works recommence
until complete.