Wednesday, 24 April 2013

The site team are excited to see the installation of the block and beam floor this week. once this is completed, the insulation can be laid down and the concrete floors poured. Sam Bray Assistant Surveyor on Sandymount said "It's good to see the men are braving the weather to get the block and beam down so follow on trades can commence in line with the programme"
 
 
 

Thursday, 18 April 2013

Ivor Goodsite visits Golcar Gala 22nd June.

The site team have commenced the organisation of Wates' involvement in the Golcar Gala in June, we will have a JCB Excavator in attendance with our designated driver Ivor Goodsite! Ivor will be supported by a number of our colleagues from the Kirklees schemes where photographs, key rings and pictures with Ivor will be available. We look forward to seeing all our friends and colleagues at the event, tickets are available from our project office.

Crosland Moor Junior School Poster Competition

Samuel Bray, Quantity Surveyor on the Sandymount project has visited Crosland Moor Junior School to start the Site Safety Poster competition, The poster competition has been used really well historically on informing younger children on the safety needed on site, this will be run with the Hunt the Hazard initiative.

Friday, 12 April 2013

80% of the drainage is now completed on site and we are preparing the site for the construction of the block and beam.



Friday, 5 April 2013

We finished 30% of drainage at the end of this week.