The team at
Sandy Mount would like to wish everyone a happy new year and we hope that
everyone enjoyed their Christmas break. The clock has started ticking for
completion of Sandymount so its all hand on deck. All of the plastering is
complete on the second and first floors and is nearly complete on the ground.
Decoration to both first and second floor is well underway in line with the
programme and by the start of next week we should see external works recommence
until complete.